Rowan County entered into an agreement with HDR Engineering, Inc in January of 2021. The Landfill Consulting Master Agreement was approved on 1/19/2021, Agenda item J. The Board of Commissioners has approved to Award the Phase V to NJR, 1/17/2023 Agenda item 13. The County request approval on Task Orders 2023-01 and 2023-02 with HDR, not to exceed $607,200.00
Task order 2023-01 is for HDR to provide engineering services for conducting construction administration and construction quality assurance (CQA services for construction of a nineteen-acre cell of the Phase V unit of the Rowan County Landfill).
Task order 2023-02 is for HDR to provide engineering services for the abandonment of 11 piezometers and 4 landfill gas wells, as well as installation of 4 new landfill gas monitoring wells.
Attached are the two task orders submitted for approval.
Recommendation: Board of Commissioners authorize County Manager to approve Task Orders 2023-01 and 2023-02 with HDR, not to exceed $607,200.00
|