Mid-Carolina Airport awarded a contract to JT Russell & Sons for the construction of a parking lot near the hangar leased by Retail Business Services (Food Lion). The bids were opened June 29, 2022. The original contract was for $78,7450. Change order #1, for $11,849.25 was approved towards the end of the project for additional dirt and asphalt, along with a drain extension. This brought the total cost to $90,299.25. With the recent rain the need for supplementary erosion control was discovered and a second change order needs to be approved. This change order is for $3,000, bringing the total cost to $93,299.25.
Attached is the change order from JT Russell & Sons.
Board of Commissioners to authorize the County Manager to approve a second change order with JT Russell & Sons for $3,000 for the airport parking lot bringing the total cost not to exceed $93,299.25.
| | |