Please find attached a change order 004 from Dellinger, Inc for some cost savings from the Water System Chemical Booster Project. When the fire hydrant was relocated per the design, Dellinger was able to have an onsite discussion with SRU that eliminated the need for a tap and sleeve valve during the installation. This change order reflects that cost savings of $2,693.82. This reduces the total cost of the project to $823,698.33.
Attached Change Order 004..
Board of Commissioners to authorize the County Manager to sign Change Order 004 with Dellinger, Inc. to reduce the contract by $2,693.82.
| | |