On January 3, 2022 Consent Agenda Item X was approved by the Board of Commissioners for RFC 002 and RFC 003. This item combines these 2 changes into Change Order 001 for $76,823.10 bringing the total contract cost to $819,723.51.
Attached is Change Order 001 with backup of RFC 002 and RFC 003
The Purchasing Director request that the Board of Commissioners authorize the County Manager to sign Change Order 001 to the contract with Dellinger, Inc for the NE Rowan County Chemical Booster Station bringing the total cost to $819,723.51.
| | |