Rowan County has a current agreement with Dellinger, Inc. for work related to the Chemical Booster Station. This work requires two (2) change orders that are explained below.
· Change order RFC-002 covers the new 40 kW Generator and associated work not to exceed $74,672.53
· Change order RFC-003 covers additions to Lord & Company’s programming scope for metering pump controls that were added to meet the State’s request for additional monitoring not to exceed $2,150.57
Attached are both change orders RFC-002 and RFC-003 and Summary showing new total cost of project.
Purchasing Director recommend that the Board of Commissioners authorize the County Manager to approve changes orders RFC-002 not to exceed $74,672.53 and RFC-003 not to exceed $2,150.57 with Dellinger, Inc. for work at Chemical Booster Station bringing the total cost of the project to $819,723.51.
|